Main Street Lighting Project

1/12/2024

Dear Resident/Business Owner

 

Main Street Lighting Upgrades, Medford Township, Burlington County New Jersey

This letter is to advise you in advance of street lighting upgrade construction on Main Street.

 

WHAT TO EXPECT:

 

· Conduit and Street lighting construction.

· Work Hours 7:00 am to 5:30 pm Monday through Friday.

· Work will take place on Main Street between Route 70 and Trimble Street.

· When it is expected to start on January 22, 2023, and anticipated duration of 8 – 10 Months.

· Traffic will be maintained in each direction at all times during the construction process.

· Parking restrictions will be implemented in the immediate area of construction.

· Access for pedestrians will be impacted in the immediate area of the construction.

· Access for the Fire Department and Emergency responders will be maintained.

· Accessibility to homes and businesses will always be maintained.

 

We thank you in advance for your patience and cooperation during these essential works. If you have any questions or comments about this project, please feel free to contact us.

 

Contact Information:

 

ERI Engineering: Alette Knoblauch – 856-600-7288

Kane (contractor): Gerald Sterner – 267-908-0378 Project Super

Kane (contractor): Jim White – 609-760-5726 Project Manager