How long does it take to get a permit for construction?

If the application for the permit has already received all “prior approvals”, we will review your application within as little as a few days to a maximum of 20 business days, depending on the complexity of the project and, our current workload. If the application is for a simple interior alteration (finishing a basement, moving a wall, etc) the review period will only be a few days; if there are any deficiencies in the application, you will be advised in writing of just what additional or corrected information is needed. If the application is for a new home or is otherwise more complex, the review period is 20 working days maximum.

Can't find what you're looking for? Create a request for service